Follow the progress of the expansion building work at our school.

20th January 2020

Good progress is being made on the multi use games area (MUGA) being built behind the Year 6 block.
The builders are also working on drainage issues on site and waiting to use machinery currently being used on the Vandyke building site.
Both the MUGA and the drainage work are running according to
schedule.

 

10th January 2020

The contractors have moved onto site. They are tarmacking the area behind the youth club so it can be used as a temporary play area.